Who asks for the weight, and what they do with it
Every stone drawing has thickness, finish and quantity, but no weight. Why the figure is always estimated, and what each trade needs from it.
4 November 2026 · 14 min read · GranTerra Stone, Hui'an
Open a set of shop drawings for a stone job and count the fields. There is a piece number, a material, a thickness, a finish, an edge detail, a quantity and a destination. There is no field for weight. The one property that decides whether the slab can be stood on, lifted through a window, carried up a stair or sent on a lorry with anything else is the one nobody writes down, and it is the one that gets estimated out loud, in a corridor, by somebody who is in a hurry.
That is not a scandal. Weight is derivable — volume times density — and everyone involved knows it is derivable, which is exactly why nobody insists on the number. The engineer assumes the architect has it. The architect assumes the supplier will confirm. The supplier gives a figure when asked, honestly, quickly, and usually without saying what it includes. Three months later that figure is inside a structural calculation, a lift booking and a customs document, and it is being used as though it were measured rather than estimated.
What follows is about that number: who asks for it, what each of them is really asking, why the same piece can honestly have four different weights, and what a supplier can put in writing that will survive being used by people who were not in the conversation.
The figure that is never printed on the drawing
Every other stone property on a drawing is a decision. Thickness is a decision. Finish is a decision. The edge is a decision. Weight is not a decision; it is a consequence of the decisions, and consequences are the first thing to fall out of a document.
This matters because of how a project is checked. A drawing is reviewed field by field, and a field that does not exist cannot be reviewed. So the weight of a stone element is rarely questioned at design stage and almost always questioned at installation stage, by which time the answer is expensive to change. A cladding panel that is heavier than the fixing was designed for is not a drawing error. It is an omission, and omissions are harder to pin on anyone.
The same silence runs the other way. When a buyer asks for a price and gets one, the price has in it an assumption about how many pieces go in a crate and how much a crate is allowed to carry. Nobody sees that assumption either, which is why two quotes for one drawing can land far apart without either supplier having moved a rate.
One piece, four different weights
Suppose a piece leaves the works. Before it reaches the building it will be weighed, in some sense, four times, and the four answers will not agree.
The first is the dry weight of the finished stone, which is what a density figure is for. The second is the same piece with water in it. Granite takes on very little water compared with a porous limestone, but the surface carries a film after wet sawing, and a piece that has stood outside for a week is not the piece that was measured in the workshop. On a large element the difference is small; on a whole crate of them it is not nothing.
The third is the piece as reinforced. Backing mesh, a resin coat, a steel or fibre insert on a thin section: these are not stone, they are part of the object, and they add weight to the thing that has to be lifted. The fourth is the piece as packed, which is where the arithmetic really drifts, because a crate is wood, foam, battens, straps and a pallet, and none of that is the stone but all of it is on the scale.
Four numbers, one object. A figure that does not say which of the four it is has not answered the question, even when it is accurate. The same ambiguity runs through the units a job is counted in, which is the ground covered by the note on how quantities are counted.
A range is more honest than a number
The instinct is to give one figure, because one figure sounds confident. In practice a range with its assumptions attached is more useful and more likely to be right.
A dense granite varies in density across the family, so the same volume can legitimately weigh different amounts depending on which stone it is. Add the variables above and the honest answer for a batch is a band, not a point. What makes the band usable is the note beside it: this is dry stone, without packing; this includes the crate; this is per piece, and there are this many pieces in the box.
That is a different kind of document from a spec sheet. It is a working note, and it is worth more to the people downstream than a precise-looking number with no boundary around it. An engineer can check a range against a capacity. A haulier can plan against a range. A site foreman can look at a range and decide whether to book a hoist. None of them can do anything sensible with a figure they do not know the edges of.
What the structural engineer does with it
An engineer is rarely interested in the total. A tonne of stone spread over a floor is a different proposition from the same tonne arriving on four small feet, and the whole of structural review is about which one it is.
So the useful package for that conversation is not the weight on its own. It is the weight of the heaviest single piece, the area over which that piece touches what holds it up, and the position on the plan. A carved basin, a tub, a heavy table, a stone pier base, a sculptural element on a roof terrace: each of those is a point load, and the structural question is where the load lands rather than how big the order was.
We can supply those three facts. We cannot supply the conclusion. Whether a floor, a deck or a transfer structure can take the load is a question for somebody who has seen the building, and a supplier who answers it from a workshop is guessing with somebody else’s insurance. The note on freestanding stone tubs sets out the same division of labour for the heaviest single object we make, and it applies to every other heavy piece in the same way.
What the haulier works out for themselves
Freight does not ask how much a piece weighs in the abstract. It asks whether the load can be placed, secured and legally carried, and those three questions are answered by a different set of numbers: the weight of the whole consignment, how that weight is distributed along the vehicle, how high the centre of gravity sits, and whether the pieces can be stacked or must travel on edge.
This is why a supplier’s figure is only an input. A crate that is dense and low behaves well on a lorry; a tall crate with a heavy top does not, and the fix is packing rather than arithmetic. A single piece beyond what a tail lift will take changes the delivery from a van and two men to a flatbed and a crane, and that change is decided by one number crossing one threshold, not by the total.
The loading side of this is covered in the note on how a stone order ships. What belongs here is the ordering problem: the decision that turns a crate into an awkward crate is made at the saw, when pieces are grouped, long before anybody books a vehicle. Posts and bollards are the clearest case in the catalogue, since a run of identical pieces crates beautifully and then has to be lifted one at a time at the other end — the note on that product follows the same problem down to the kerb.
Two numbers that only mean something together
Ask three people whether a piece will get into a building and you will get three confident answers based on three different concerns. The designer looks at the opening. The site looks at the stairs. The supplier looks at the weight. The piece arrives, and the answer turns out to depend on all three at once.
A stone element has to pass a door, a turn, a stair, a landing and, in most commercial buildings, a lift. Each of those is a gate with two dimensions and a capacity, and the piece has to clear all of them in the same movement. A panel that fits the doorway can be too long for the turn at the top of the stair. A piece that fits the stair can be too heavy for two people to carry up it, which is a different failure with the same result.
A lift is the clearest case, because a lift is rated for a load and dimensioned for a crowd. The rated load is not the only limit; the clear height, the door width, the threshold and the depth of the car all matter, and a service lift that takes a trolley of linen is not automatically a lift that takes a stone panel on a stillage. Once a heavy piece is inside a finished building and turns out not to fit, the cost is no longer about the stone. It is about the wall that has to come out.
The survey that prevents this takes half an hour and is usually skipped, because it belongs to no single trade. It means walking the route with a tape and recording the narrowest point rather than the widest door: the clear width between a handrail and a wall, the height under a service duct, the depth of a lift car with its doors open, the step at the top of a stair. Those are the numbers that decide whether a piece can be delivered, and none of them appear on the drawing that describes the piece.
The limit of a pair of hands
There is a figure in every site discussion that never appears in any document: what two people can actually carry. It is smaller than most people assume, it depends on shape as much as mass, and it is the reason a lot of stone arrives intact and then gets damaged in a corridor — a stretch of the story that protecting stone on site takes further.
Shape is the part that surprises people. A compact block can be held close to the body. A long piece — a worktop, a tread, a coping — puts the mass far from the hands, and the further it is, the more of the effort goes into stopping it from rotating rather than into lifting it. The tread is the standard case, and the note on stair treads deals with the setting out that has to happen before the carrying does. Two people carrying a long piece on a stair are also, in a practical sense, one person carrying it, because only one of them has a hand where the weight wants to go.
Suction cups help with flat faces and are useless on a moulded edge. A stillage helps until it has to go up a step. And the common site answer — bring more people — runs out of room on a stair, where four people cannot stand where two were standing. This is why a practical maximum on the single piece belongs in the order, decided at the drawing stage, rather than being discovered on the day by whoever is holding the heavy end.
Where an approximate figure ends up
Trace a figure through a project and you can see how a reasonable estimate becomes an unreasonable argument.
It starts in an email, as an answer to a plain question, and it is given quickly because it is easy to derive. It is then copied into a structural note, where it loses the word “about”. It is copied again into a lifting plan, where it gains a safety margin that may or may not be on the right side. It appears a third time on a packing list, where it is a different number because the crate is included, and now two documents in the same project disagree.
Nobody has behaved badly. What has happened is that an estimate was promoted to a fact by being copied, and copying removes context. The way to prevent it is not to be more careful in the email. It is to give a figure that carries its own conditions, in a form that survives being pasted somewhere else — which usually means a small table rather than a sentence.
Where two documents in the same project disagree, the one that gets believed is the one with a letterhead. A packing list from the works will beat a figure in a covering message, even when the same person wrote both, and neither will be checked back against the drawing. That is an argument about authority rather than accuracy, and the only defence is to nominate one document that everybody is told to quote from. The crate carries a number for exactly this reason, as the note on marking explains: a weight with no piece attached to it is a rumour.
The five lines that go out with the confirmation
For an order where weight is going to be used by other people, the note that goes out with the confirmation carries five things.
The weight of the heaviest single piece, as a band, with packing excluded and stated as excluded. The weight of a full crate, with the number of pieces in it, so that a haulier can work in crates rather than in stones. The footprint — the area through which the heaviest piece meets what holds it — because that is what a structural check actually needs. The pieces that must travel on edge or cannot be stacked, because that decides the shape of the load. And, for anything that will be lifted by machine, a note on where the centre of gravity sits and where it is safe to sling.
None of this is a structural opinion and none of it is a promise about a building. It is a description of the object we are making, in the units the next three people in the chain will use it in. It costs nothing at the point of order and it is expensive to reconstruct afterwards, which is the whole argument for doing it early.
Ask with the drawing, not after the order
The question that produces a useful answer is not “how much does it weigh”. It is the same drawing with four notes added: what the pieces will rest on, how they will get to that point, whether anything will be lifted by machine, and whether the destination is a ground floor or something higher.
From those four notes we can tell you which figure matters, give it a band and a boundary, and flag the one piece in the order that is going to be the awkward one. That flag is usually worth more than the number, because the awkward piece is the one that changes a delivery, a lift booking or a fixing detail — and it is much cheaper to change those on paper than in a finished building.
If the drawings are still moving, send what you have. A section, a plan and the route into the building are enough to start, and the note on ordering from a drawing explains what we do with them. The number can follow the shape; it is much harder the other way round. Send the four notes with the drawing through the enquiry form, and the reply will name the awkward piece before anything is priced.
Every figure on this page comes from our own order sheets. Where something is a trade norm rather than a number we can hold, we say so — send a spec and we will confirm it against a real block before you commit.