The half of the job that is not in the quote

A stone price usually covers supply, not fixing. Where the boundary falls, what the installer needs from the factory, and what a buyer must add.

5 November 2026  ·  14 min read  ·  GranTerra Stone, Hui'an

A finished white marble reception desk in a showroom, installed and lit, with the joints following the veining

Ask a buyer what they have bought and they will describe a finished surface: a wall that reads as one plane, a floor that takes a heel without chipping, a counter that meets the wall with a line fine enough to be a shadow. Ask what the invoice actually covers and the answer is a stack of pieces on a lorry, measured, packed and numbered, sitting at a port.

Between those two descriptions is the whole of the installation, and it is the part of a stone project that most often has no owner at the moment it is priced. The supplier has quoted stone. The builder has allowed for a finish. Somebody has assumed that somebody else is bringing the men, the adhesive and the lifting gear, and nobody has written it down, because at tender stage it looks like a detail and at handover stage it is the only thing left.

This is a note about where that line falls, why it falls there, and what a buyer should put on their own side of it. It is written from the supply side, because that is the side we are on, and being clear about what we do not do is more useful to a project than a promise we cannot keep from four thousand miles away.

A price for stone is not a price for a wall

Stone leaves a works as an object, not as a building element. What we sell has a size, a finish, an edge and a number. What a building needs is that object held in place, level, plumb, jointed, sealed and safe, on a substrate that somebody else has prepared and somebody else will warrant.

Those are two different trades with two different sets of risks. One is about material, machining tolerance, packing and freight. The other is about access, sequence, weather, labour and the state of the wall behind. They meet at the moment the crate is opened, and everything before that moment is ours while everything after it belongs to somebody standing on the site.

When a buyer compares two numbers for the same drawing and finds one dramatically lower, the difference is very often not the stone. It is that one number includes fixing and the other does not, and neither document says so in the same words. The note on comparing quotes goes through the other reasons the numbers separate; this one is about the largest of them.

Where the line is actually drawn

There is no single convention, which is precisely why it has to be stated on the quote rather than assumed. In practice the boundary sits at one of four places, and each of them leaves a different set of tasks on each side.

The first is ex works: the buyer’s freight forwarder collects, and everything from the works gate onwards is theirs. The second is delivered to port, cleared for export. The third is delivered to the site address, which still says nothing about who unloads, where the pallets go, or whether a forklift will be available at nine in the morning. The fourth is delivered and placed in the room, which is the nearest thing to installation a supplier can offer and is really a logistics service rather than a fixing one.

Whichever is written, the tasks on the far side of it do not disappear. Somebody still has to receive, check against the packing list, move the pieces to the floor they belong on, protect them from the other trades, set out the first line, cut the pieces that need adjusting on site, fix them, joint them, and clean them down at the end. A supply-only price is honest about all of that only if it says, in words, that none of it is included.

Unloading is where the wording most often goes soft. Delivered to site sounds like an end point, but a lorry on a street is not stone in a room. Between those two states sit a parking space, a forklift or a crane, a route across a finished floor, a lift with a load limit and somewhere the crates can stand without blocking whoever comes next. Each of those is somebody’s job, and on a supply-only order none of them is ours. The note on shipping ends where this paragraph begins: with a vehicle at the kerb and a building behind it.

Why an exporter stops at the kerb

It is worth saying plainly why a factory in one country rarely installs in another, because the reason is not reluctance to earn the margin.

Fixing stone is regulated work almost everywhere. It touches structural fixing, fire performance, waterproofing and, in wet areas, the tanking that has to be signed off before a tile goes on. It carries insurance obligations, and it carries a warranty that has to be honoured by somebody who can return to the building within a day. A supplier working across an ocean can meet none of those conditions. It cannot send a gang for a week and get them back for a snag list, and it cannot carry a local liability it has no way to discharge.

There is a practical constraint on top of the legal one. Installation is a sequence, and a sequence is driven by other trades: the screed that is not dry, the waterproofing that failed a flood test, the window that arrived late, the scaffold that came down early. None of that is in a stone supplier’s control, and a price that includes labour has to absorb it. A factory that quotes fixing from overseas is either pricing a risk it cannot see or planning to argue about it later.

What the installer needs that is not on the pallet

Because we do not fix, the handover has to be more complete than it would be between a local fabricator and a local gang who have worked together before. Four things travel with the stone that are not stone.

The first is the setting-out information: where the first piece goes, which way the pattern runs, where the cut pieces are, and which pieces are numbered to meet which. This is the same information that made the crate possible, and it is worthless if it stays in our office. The note on working from a drawing describes how that information is produced in the first place. The second is the fixing method the pieces were designed for. A panel detailed for a dry-hung bracket is not a panel that can be dot-and-dabbed, and the difference has to be stated rather than inferred from a section on a drawing nobody on site has opened — the note on interior panels sets out how far apart those two methods really are.

The third is the consumables list: the adhesive family that suits the stone, the sealant that will not stain it, the anchor type, and the joint width the layout assumes. The fourth is repair material for the same batch, because a chip on site is normal and a chip that cannot be filled with matching material is a visible fault. The note on why the spare has to be in the first order explains why that last one cannot be solved later.

Three things the buyer has to add to the number

If the price in front of you is supply-only — and on most export orders it is — then the number that matters is not that price. It is that price plus three things.

The first is the fixing labour, and it is the one item that varies most between markets for identical work. The second is the consumables and the plant: adhesive or mortar, anchors, sealant, blades, a wet cutter, suction cups, a hoist or a genie if the pieces are heavy and the route is awkward. These are small line items individually and a real sum together, and they are almost always omitted when a buyer first compares a landed stone price with a local installed rate.

The third is breakage and adjustment, and it is the one people underestimate. Some pieces will be cut on site because a wall is not as square as the drawing. Some will be damaged in handling through somebody else’s doorway. Budgeting nothing for that is not optimism, it is a decision to have the argument later, and it usually surfaces as a request for urgent replacement pieces at air-freight prices. A percentage held against the order, agreed at the start, is cheaper than either.

There is a fourth item that belongs on the buyer’s side and almost never appears in a budget at the start: the conditions the installer will refuse to work without. Stone is usually the last trade into a wet area and the first to be blamed when the tanking underneath it was never flood-tested. The same applies to a screed that has not dried, a wall that is out of plumb, and a substrate that was never specified for the weight being hung on it. The note on wet rooms deals with that interface, and the point here is a scheduling one: those conditions cost nothing to check early and a fortnight to fix late, and no fixing price on earth includes waiting for them.

The gap that belongs to nobody

The most expensive failure in a supply-only project is not a bad piece of stone. It is a piece that arrives intact, is signed for, and is found damaged three weeks later when the gang opens the crate.

At that point four parties can each make a reasonable case. The supplier has a photograph of the crate sealed at the works. The forwarder has a clean bill. The site has a signed delivery note with no comments on it. The installer says the crate was already like that. Nobody is lying, and nobody is going to pay, and the piece still has to be replaced.

The way out is not more careful language in the contract. It is a procedure that takes twenty minutes on the day: open every crate on arrival, check the pieces against the packing list, photograph anything that looks wrong before it is moved, and write the exception on the delivery note before signing it. That single habit moves the argument from three weeks later, when nothing can be proved, to the afternoon of delivery, when everything can. The note on what a site does to new stone covers what happens if the crates are left closed and in the way.

When one contract is the better answer

There are projects where a single contract, covering supply and fixing, is genuinely the right structure, and it is worth being honest about which ones they are.

A small domestic job with a local mason is one. The quantity is low, the risk of a shipping error is real, and the person cutting the stone is the person who measured the room, which removes an entire category of argument. A mock-up or a sample installation is another: if the point of the exercise is to prove that a detail works, the detail should be built by the people who proposed it. A refurbishment where the new stone has to meet existing stone on the same plane is a third, because that is joinery rather than supply, and joinery depends on what is actually there rather than what the drawing said. Where stone meets another material has its own note, and it is the part of a refurbishment that a supply contract handles worst of all.

What those cases share is that the fixing is close to the making. Where the fixing is far away, spread across many trades and many weeks, a single contract is usually a promise about coordination that no single party can keep — and the coordination is what fails, not the stone.

What we do more of, because we do not install

Not installing changes how an order is prepared, and it changes it in directions a buyer can check.

The packing gets more conservative, because the crate has to survive a longer journey and a rougher handover than a local delivery would. The numbering gets finer, because nobody on the far side can ring the works and ask which piece was meant for the return. The marking scheme has to work for a gang who have never seen the drawing set, which means the crate and the elevation have to agree without a phone call.

Extra material goes in more often, because a piece broken in a distant city is a longer problem than a piece broken down the road. And the documents get more attention than they would in a domestic supply, since the only thing that can substitute for a person on site is a written instruction clear enough that nobody has to guess. That is not a virtue. It is what the distance forces, and it is the reason a supply-only price from a serious exporter is not simply a local price minus the labour.

Distance also changes what a question costs. A fitter who finds a piece that will not sit can walk to the van and cut another one before lunch. From here the same question takes a day to be asked, a day to be answered and a week to be shipped, which is why the pieces most likely to need adjusting on site are the ones we spend the longest on before they are packed. It is cheaper to be slow at the saw than slow at the wall.

Making the handover a document

The handover should not be a conversation at the gate. It should be a small pack that a site manager can read in ten minutes and keep.

It has five parts: a layout that shows where the first piece goes and which way the bond runs; a piece list that ties every number to a position; the fixing and consumables specification with the assumptions behind it; the delivery sequence, so that the pieces needed last are not at the back of the container; and the name of the person who can answer a question about a specific piece, with the time difference stated rather than discovered. Everything else is optional, and most of it is genuinely not needed.

What makes the pack work is that it is written for a reader who was not in any of the earlier conversations. That is a harder document to produce than a covering email, and it is the only one that survives being forwarded to a foreman on a Friday afternoon.

Ask which half you are being quoted

The question is short enough to put in the first email: does this price include fixing, and if not, where does your responsibility end? A supplier who answers it precisely, with the boundary named, is telling you something about how the rest of the order will be handled.

If the answer is supply only, the next question is what the handover pack contains, because that is the part of the job we can actually control from here. A short message through the contact page, with a drawing attached, is enough to establish which half of the work is being discussed, and knowing that is worth more than a lower number that turns out to be for the other half.

The stone is the easy half. It is the half that arrives in a crate with a number on it. Whether the project finishes quietly depends on what happens in the eight hours after that crate is opened.

Written in the yard

Every figure on this page comes from our own order sheets. Where something is a trade norm rather than a number we can hold, we say so — send a spec and we will confirm it against a real block before you commit.

Next step

Send the drawing. We do the rest.

Reply within one working day, in English or Chinese. Send a spec, a drawing or just a photo of the sample you are matching — we will tell you honestly whether we can hold it.

MOQ 1 × 20FT  ·  FOB XIAMEN  ·  SAMPLES IN 7 DAYS

Chat with us on WhatsApp